Money Can Build Fabs. Why Not a Chip Supply Chain?
Because every layer has its own bottleneck, and the bottlenecks sit in different countries. Diversifying design does not offset concentration in manufacturing either: the two are risks at different layers.
What layers does a chip pass through?
For three decades, semiconductors have been one of globalisation’s most refined divisions of labour: the United States in design and EDA software, Japan in materials and certain critical equipment, the Netherlands’ ASML in advanced lithography, Taiwan in leading-edge processes and foundry manufacturing, South Korea in memory, and China in final assembly and as an enormous market.
The system rests on cost, efficiency, and specialisation, and it has helped drive down the price of smartphones, cloud computing, and consumer electronics.
This is not one production line that can be moved wholesale. It is six layers, each developed separately over decades, and none of them can be replicated just by building a plant.
Why does each layer come down to a handful of firms?
Because at every layer the barriers to entry compound. Equipment sells only once someone is willing to risk a production line to qualify it; a process matures only after enough volume production to bring yields up; materials often take more than a year to certify. The gap a newcomer faces is one of time rather than technology, and the leaders do not stop to wait.
That is why subsidies can build a fab but cannot buy yield. A building is a matter of capital; yield is a matter of experience.
Where do single points of failure usually hide?
Usually not in the most expensive or most visible step. A single point of failure is more often a speciality chemical, a single packaging plant, or a particular inspection tool: a tiny share of the cost, yet without it the line stops.
They are hard to find because they tend to sit with third- or fourth-tier suppliers, while most firms can see only the first tier. Knowing your suppliers does not mean knowing your suppliers’ suppliers.
For the same reason, “we have two suppliers” does not necessarily mean redundancy: both may buy the same material from the same source.
Do overseas fabs solve the concentration problem?
They reduce the risk tied to any single site, but they do not make the layer any less concentrated. A new fab still needs the same equipment, the same materials, and the same experienced engineers; the location changes, but the bottlenecks upstream and downstream do not.
Expansion also takes years. TSMC is expanding 3nm-related capacity in Taiwan, the United States, and Japan, with output ramping up through 2027–2028, several years after its second fabs in the United States and Japan were first announced.
Any discussion of resilience has to separate two risks. One is that something goes wrong in a single place, which geographic dispersion can address. The other is industrial concentration: only a few firms in the world can do the work at all, and that cannot be fixed in the near term.
How reliable is the “silicon shield” argument?
The silicon shield argument holds that Taiwan’s irreplaceable position in the chip supply chain is itself a deterrent: destroying that capacity would do grave damage to the world economy, so every side has an incentive to preserve the status quo.
The objection is that the argument assumes rational calculation will outweigh political motive. History has no shortage of costly conflicts, and “very costly” does not mean “will not happen”.
Overseas expansion is read in two ways: as spreading risk, and as diluting the shield. Both readings hold, because they answer different questions. One asks whether the capacity is safe; the other asks whether Taiwan’s bargaining position has changed.
Sources
- Semiconductor Industry Association (SIA) and Boston Consulting Group (BCG), Strengthening the Global Semiconductor Supply Chain in an Uncertain Era, Apr 2021
- McKinsey & Company, Supply chain risk pulse 2025: Tariffs reshuffle global trade priorities, 2 Dec 2025
- Central News Agency (CNA), AI需求強勁驅動台積電成長逾30% 法說會重點一次看, 16 Apr 2026
- TSMC, TSMC Announces Updates for TSMC Arizona, 6 Dec 2022
- TSMC, JASM Set to Expand in Kumamoto Japan, 6 Feb 2024